PH 2017-38: Proposed SW Plaza Parkway and SW College Ave Detention Basins Project
EXECUTIVE SUMMARY:

The SW Plaza Parkway and SW College Ave Detention Basins Project includes

the construction of two stormwater detention basins and general grading. The basins are located in the southwest area of Prairie Trail in Ankeny, on the west side of SW College Avenue and south side of SW Plaza Parkway.

 

The construction improvements for the stormwater detention basins include storm sewer installation and 102,500 CY of Class 10 earthwork excavation. Other associated improvements include pond clay liner, dewatering, revetment, trees, armor mat, temporary erosion and sediment controls, seeding and fertilizing and miscellaneous associated work. Phase 1 includes all items shown in contract documents, except for Native Seeding. Phase 2 is only the Native Seeding.

 

The bid opening for the project was held on Wednesday May 31, 2017.  Four (4) bids were received as follows:

1.  Seamus Excavating, LLC                   $855,070.38
2.  McAninch Corporation                        $873,100.00

3.  Quam Construction Company, Inc.    $917,299.08

4.  Vanderpool Construction, Inc.            $1,101,869.00

 

 

The engineer's estimate for the project was $1,456,799.00.  The bids ranged from approximately 41% below to 24% below the engineer's estimate.  Public Works staff reviewed the bid results internally.   Seamus Excavating, LLC has not previously completed public improvement projects for the City, but based on their references and relevant project experience they have the technical experience to undertake this project.  It is recommended that the project be awarded to Seamus Excavating, LLC of Clive, Iowa.
 
Pending project approval and award by the City Council, the contractor will be required to fully complete the work within 45 working days with a late start date of July 17, 2017 for the Phase 1 work.  The Phase 2 work shall be started between November 1, 2017 and November 15, 2017 and the contractor will be required to fully complete the work within 10 working days.  The Notice to Proceed is expected to be issued in June 2017.

FISCAL IMPACT: No
This project is included in the City's current Capital Improvements Program with construction scheduled for 2017.
CITY MANAGER'S RECOMMENDATIONS:
1.  Hold a hearing on the proposed Contract Documents (plans, specifications and form of contract) and estimated cost ($1,456,799.00).

2.  Approve Resolution, adopting said plans, specifications, form of contract and estimated cost for the SW Plaza Parkway and SW College Avenue Detention Basins project.

3.  Receive and file the report of bids received on May 31, 2017.

4.  Approve Resolution making award of construction contract to Seamus Excavating, LLC of Clive, Iowa.

5.  Approve Resolution approving contract and bonds with Seamus Excavating, LLC in the amount of $855,070.38.
PREVIOUS COUNCIL/COMMISSION/BOARD ACTION(S):

May 1, 2017: The City Council approved a Resolution ordering construction and setting the public hearing date as June 5, 2017, in accordance with the Notice to Bidders and Notice of Public Hearing which was posted on the Iowa League of Cities and Master Builders of Iowa websites on May 5, 2017 and published in the Des Moines Register on May 19, 2017.

PUBLIC OUTREACH EFFORTS:
ACTION REQUESTED:

Action: Consider motion to close Public Hearing 2017-38

ADDITIONAL INFORMATION:
ATTACHMENTS:
Click to download
PH Coversheet
RES - plans, specs
Bid Sheet
Bid Tab
RES - making award
RES - approving contract
Location Map