The Fire Station No. 3 Construction Project includes the construction of a new, single story station that is approximately 12,260 SF in size located on the north side of NE 36th Street at the entrance to Otter Creek Golf Course. The station that will be built will be very similar to Fire Station No. 2 on SE Oralabor Road, with three possible exceptions. There are four deduct alternates that are included with the base bid:
1) Remove the upper windows and lower the roof over the entry lobby.
2) Remove the upper windows and lower the roof over the apparatus bays.
3) Remove one of the three apparatus bays.
The station construction will be masonry walls with exterior brick, steel framing and metal stud walls. The wall finishes and color schemes will closely resemble those at Station No. 2. A concrete reinforced safe room will be constructed within the station as well. Construction will include grading, geothermal, civil, structural, mechanical, electrical and technology systems needed to provide a complete, functioning fire station.
The bid opening for this project was held on Tuesday, July 11, 2017. Nine bids were received as follows:
1. DDVI Inc. (Indianola) |
$ 3,305,000.00 |
2. Jensen Builders (Ft. Dodge) |
$ 3,400,000.00 |
3. Henkel Construction (Mason City) |
$ 3,407,000.00 |
4. Rochon Corporation (Urbandale) |
$ 3,453,000.00 |
5. HPC LLC (Ames) |
$ 3,470,000.00 |
6. Ball Team LLC (Urbandale) |
$ 3,524,000.00 |
7. Dean Snyder Const. (Ankeny) |
$ 3,550,000.00 |
8. Koester Construction (Grimes)
9. Lang Construction Group (WDM)
|
$ 3,580,000.00
$ 3,597,000.00
|
The engineer's estimate for the project was $4,136,003.00. The bids were very close and ranged from approximately 20% below to 13% below the engineer's estimate. SVPA is familiar with DDVI Inc., and this firm has done projects of this scope in the past. They are currently working on one of the elementary school expansion projects within Ankeny. It is recommended that the project be awarded to DDVI Inc., of Indianola, Iowa, with a base bid amount of $3,305,000.00. If Council chooses to accept the alternates as defined above, the contract amount would be reduced to the following values:
Alternate 1 = $ 3,257,000.00 (deduction of $48,000.00)
Alternate 2 = $ 3,279,000.00 (deduction of $26,000.00)
Alternate 3 = $ 3,226,000.00 (deduction of $79,000.00)
Alternate 4 = $ 3,219,000.00 (deduction of $86,000.00)
It is recommended that the council accept the base bid from DDVI Inc. in the amount of $3,305,000.00 without exercising any of the four deduct alternates from the bid. Pending award, the contractor would start work on August 3, 2017 and would have until September 1, 2018 to fully complete the station. |