Resolution
LEGAL:
No Review Required
SUBJECT:
Consider motion to adopt RESOLUTION accepting a proposal from Pine Grove Nursery in the amount of $80,286.00 for the construction of the NE 36th Street Landscaping Improvements project.
EXECUTIVE SUMMARY:

The action before the Council is the adoption of a Resolution accepting a proposal from Pine Grove Nursery for the NE 36th Street Landscaping Improvements project.

 

The NE 36th Street Landscaping Improvements project includes the installation of trees and grasses along each side of NE 36th Street located between Ankeny Boulevard (US Hwy 69) east to NE Delaware Avenue in the City of Ankeny.  The construction improvements include the installation of 27 2" cal. Overstory Trees, 56 2" cal. Understory Trees, 7 6' height Evergreen Trees, and 794 Ornamental Grasses.  Other associated improvements include traffic control, mulched planting beds, and miscellaneous associated work necessary to complete the project.

 

Bid invitations were sent to 13 contractors.  Two (2) bids were received for the project as follows:

 

1.  Pine Grove Nursery                    $80,286.00

2.  Country Landscapes, Inc.         $117,873.00

 

The Engineer's Estimate for the project was $98,363.50  The bids ranged from 18% below to 20% above the Engineer's Estimate.  Pine Grove Nursery has completed similar work as a sub-contractor on previous arterial roadway reconstruction projects for the City of Ankeny and they have the technical experience and capacity to undertake this project.  The Public Works Department recommends award of the NE 36th Street Landscaping Improvements project to Pine Grove Nursery of Kellogg, Iowa.

 

Pending City Council approval, the Notice to Proceed for the project will be issued on or before October 16, 2017.  The contractor has 20 working days to complete the project.  The trees will be installed in Fall 2017.  The grasses and mulched planting beds will be installed in Spring 2018.  The contractor is required to maintain and water both the trees and the grasses for a period of one year after installation and replace any plants that do not survive during this one year establishment period.

FISCAL IMPACT: No
The NE 36th Street Landscaping Improvements project is included in the current 2017-2021 Capital Improvements Program for 2017-2018 construction as a part of the NE 36th Street Reconstruction - Phase 2 project.
CITY MANAGER'S RECOMMENDATIONS:
Approve the motion to adopt RESOLUTION accepting a proposal from Pine Grove Nursery for the NE 36th Street Landscaping Improvements project.
PREVIOUS COUNCIL/COMMISSION/BOARD ACTION(S):
PUBLIC OUTREACH EFFORTS:
ACTION REQUESTED:
ADDITIONAL INFORMATION:
ATTACHMENTS:
Click to download
Resolution
Bid Tabulation