The actions before the council are the acceptance of the Certificate of Completion, passage of a Resolution accepting the public improvements, and approval of the final and retainage payments to Alliance Construction Group, LLC on the S Ankeny Blvd and SE Shurfine Dr / SW Prairie Trail Pkwy Intersection Improvements project.
The S Ankeny Blvd and SE Shurfine Dr / SW Prairie Trail Pkwy Intersection Improvements project is now complete including all final punch-list items. A series of actions are needed in order to close out this construction project:
1. Approval of Final Change Order #6 increasing the contract amount by $11,734.53.
2. Engineer's Certificate of Completion: The attached Certificate of Completion from the project engineer states that the work performed was in substantial conformance with the plans and specifications, and that the final contract amount is $3,392,537.98.
3. Resolution accepting the public improvements: This resolution approves and adopts the engineer's Certificate of Completion on the S Ankeny Blvd and SE Shurfine Dr / SW Prairie Trail Pkwy Intersection Improvements project and establishes the final contract amount to be $3,392,537.98.
4. Final Payment: Alliance Construction Group = $119,757.19
Retainage Payment: Alliance Construction Group = $169,626.90
It is recommended that the retainage payment on the project be approved for payment 31 days from the date of acceptance of the project, in accordance with the terms of the contract. |