ANKENY CITY COUNCIL

Regular Agenda

March 5, 2018
5 : 30 PM

Gary Lorenz, Mayor
Mark Holm, Mayor Pro tem

Council Members: Bobbi Bentz, Jim McKenna, Kelly Whiting, Kerry Walter-Ashby
Print
ORIGINATING DEPARTMENT: COUNCIL GOAL:
Public Works Responsible Growth and Revitalization
ACTION REQUESTED:
Resolution
LEGAL:
Item Reviewed by Legal Counsel
SUBJECT:

Proposed SW Market Street Extension

Initiate Proceedings

EXECUTIVE SUMMARY:
The action before the Council is the adoption of a resolution regarding the SW Market Street Extension project which involves ordering construction, setting a public hearing date on the Contract Documents (plans, specifications, form of contract) and estimated total cost and setting a date for the filing of bids on the project.

The SW Market Street Extension project includes the construction of SW Market Street from the northerly end of the existing SW Market Street to the existing intersection with SW District Drive, construction of SW Park Square Drive from SW Market Street to the westerly end of existing SW Park Square Drive, construction of SW 16th Street from SW State Street to SW Market Street and a right turn lane on SW State Street onto SW 16th Street. 

 

The construction improvements include storm sewer installation, trenched and trenchless water main installation, earthwork excavation, subgrade preparation, subbase placement, 7” PCC street paving, 9” PCC street paving, and 6” PCC sidewalk paving.  3,400 SF of permeable parking pavers will be constructed as part of this project. Other associated improvements include temporary erosion and sediment controls, light pole installation, conduit installation, electrical work, SWPPP management, pavement markings and miscellaneous associated work.

The project is being presented for bidding at this time.  Pending project approval and award, the contractor will be required to substantially complete the project within eighty (80) working days. Substantially complete shall be defined as all utility, grading, and pavement construction being completed, with the new streets, driveways, and sidewalks being fully open to traffic. The construction of the SW State Street right-turn lane shall be completed within (14) consecutive calendar days, and must be completed by August 17, 2018 with full project completion within ten (10) working days after the project has been substantially completed.  Council approval at this time will set the following schedule for the proceedings:

1. Set Date of Bid Opening and Public Hearing: March 5, 2018

 

2. Post Notice to Bidders and Notice of Public Hearing:  March 9, 2018

3. Publish Notice to Bidders and Notice of Public of Hearing:  March 16, 2018

4. Bid Opening (10:30 A.M., City Hall):  March 27, 2018

5. Public Hearing and Award Contract:  April 2, 2018
(Hold Public Hearing on the plans, specifications, form of contract and estimated total cost, review bids, award contract and approve contract and bonds.)

FISCAL IMPACT: Yes
This project is included in the City's current Capital Improvements Program with construction scheduled for 2018.
CITY MANAGER'S RECOMMENDATIONS:
It is recommended that the Council take the following action:

1. Adopt Resolution ordering construction and setting the bid opening date as March 27, 2018 and setting the public hearing date as April 2, 2018 for the SW Market Street Extension project, in accordance with the Notice to Bidders and Notice of Public Hearing to be posted to the Iowa League of Cities and the Master Builders of Iowa websites on March 9, 2018 and published in the Des Moines Register on March 16, 2018.
PREVIOUS COUNCIL/COMMISSION/BOARD ACTION(S):
PUBLIC OUTREACH EFFORTS:
ACTION REQUESTED:

Action: Consider motion to adopt RESOLUTION ordering construction on the SW Market Street Extension and fixing a date for hearing thereon and taking of bids therefore. (date of bid-letting: 3/27/18 @ 10:30 a.m. / date of hrg: 4/2/18 @ 5:30 p.m.)

ADDITIONAL INFORMATION:
ATTACHMENTS:
Click to download
Resolution
Notice to Bidders and Notice of Public Hearing
Location Map