The engineer's estimate for the total scope of this project is $4,745,500. If the application is funded, the maximum grant award from the DOT would be $3,235,520; however, because this would be a hybrid Immediate Opportunity and Local Development Grant, the anticipated grant funding is lower than this amount. The gap between the project costs and final RISE award would be considered local match. The local match requirement will be met through the TIF rebates provided to Northern Tool and Kreg Enterprises.
If awarded RISE funding, the City would be required to bid the project and manage the project through completion. Separate agreements with Northern Tool/Ryan Companies and Kreg Enterprises/Property Owner will be drafted and brought to the Council prior to bidding the infrastructure projects. These agreements will include the reimbursement to the City of all project costs as the construction expenses are incurred. These agreements will be presented to the City Council for approval in February 2019. |