2019 North Creek Channel Flood Repair Project

Professional Services Agreement with Foth Infrastructure and Environment, LLC

EXECUTIVE SUMMARY:

The action before the City Council is the approval of a Professional Services Agreement with Foth Infrastructure and Environment, LLC for the design and bidding phase services needed for the 2019 North Creek Channel Flood Repair Project. 

The scope of the project includes the design for the construction of channel repairs to North Creek downstream of the box culvert under NW Irvinedale Drive.  These improvements will repair the areas damaged by the extreme flash flooding event that occurred on June 30, 2018.       

 

The design for the project needs to be undertaken at this time so that the project schedule can be maintained.  The Public Works Department proposes to use Foth Infrastructure and Environment, LLC to complete the necessary design and bidding phase services for the project because they have the technical experience needed for this project.  The scope of the engineering services and corresponding fees for the services are shown in the attached Professional Services Agreement.  The total fee for the engineering services is $35,650.00.

It is recommended that the City Council approve the Professional Services Agreement with Foth Infrastructure and Environment, LLC.

FISCAL IMPACT: No
This project is included in the 2019-2023 CIP with design and construction scheduled for 2019.
CITY MANAGER'S RECOMMENDATIONS:
Approve the Professional Services Agreement with Foth Infrastructure and Environment, LLC, for design and bidding phase services on the 2019 North Creek Channel Flood Repair Project in an amount not to exceed $35,650.00 and authorize the Mayor to execute said Agreement.
PREVIOUS COUNCIL/COMMISSION/BOARD ACTION(S):
PUBLIC OUTREACH EFFORTS:
ACTION REQUESTED:

Action: Consider motion to approve the Professional Services Agreement with Foth Infrastructure and Environment, LLC, for design and bidding phase services on the 2019 North Creek Channel Flood Repair Project in an amount not to exceed $35,650.00 and authorize the Mayor to execute said Agreement.

ADDITIONAL INFORMATION:
ATTACHMENTS:
Click to download
Professional Services Agreement