ANKENY CITY COUNCIL

Regular Agenda

January 7, 2019
5 : 30 PM

Gary Lorenz, Mayor
Mark Holm, Mayor Pro tem

Council Members: Bobbi Bentz, Jim McKenna, Kelly Whiting, Kerry Walter-Ashby
Print
ORIGINATING DEPARTMENT: COUNCIL GOAL:
Municipal Utilities Responsible Growth and Revitalization
ACTION REQUESTED:
Resolution
LEGAL:
No Review Required
SUBJECT:

SE Delaware Streambank StabilizationConsider motion to approve: a) Final Change Order #1 decreasing the amount of the contract by $11,677.74; b) Certificate of Completion; c) RESOLUTION accepting the public improvements with RW Excavating Solutions, L.C. in the amount of $163,423.26; and d) Final Payment #3 in the amount of $33,525.37 / Release of Retainage in the amount of $8,171.16.

EXECUTIVE SUMMARY:
The actions before the Council are the final Change Order, the acceptance of the Certificate of Completion, passage of a Resolution accepting the public improvements and approval of the Final and Retainage Payments to RW Excavating Solutions, L.C., for the SE Delaware Ave Streambank Stabilization project.
FISCAL IMPACT: No
The above payment will facilitate the final completion of this project which was funded through the Capital Improvements Program.
CITY MANAGER'S RECOMMENDATIONS:
PREVIOUS COUNCIL/COMMISSION/BOARD ACTION(S):
August 20, 2018: The council approved the contract and bond for the project.  
PUBLIC OUTREACH EFFORTS:
ACTION REQUESTED:
ADDITIONAL INFORMATION:
ATTACHMENTS:
Click to download
Change Order #1
Certificate of Completion
Resolution
Payment #3