SUBJECT:
Consider motion to adopt RESOLUTION accepting a proposal from J. Pettiecord Inc., in the amount of $54,600.00 for the construction of the 2019 - Deer Creek Trunk Sewer Extension Clearing and Grubbing project.
EXECUTIVE SUMMARY:

The action before the Council is the adoption of a Resolution accepting a proposal from J. Pettiecord, Inc., in the amount of $54,600.00 for the construction of the 2019 Deer Creek Trunk Sewer Extension Clearing and Grubbing project.
 
The 2019 Deer Creek Trunk Sewer Extension
Clearing and Grubbing project includes clearing and grubbing of trees within an existing sanitary sewer easement. The sewer easement is located along Four Mile Creek, near Deer Creek Estates. The goal of this project is to gather additional information to complete the designs for the 2019 - Deer Creek Trunk Sewer Extension project and the 2019 - NE Four Mile Drive RCB for Deer Creek project.

Bid invitations were sent to
8 contractors. One (1) bid was received for the project as follows:

J Pettiecord, Inc.                                                       $54,600.00

Dave’s Dozing and Excavating                                  NO BID

Halbrook Excavating                                                 NO BID

Huber Grading, Inc.                                                   NO BID

McAninch Corp.                                                         NO BID

Priority Excavating, LLC                                            NO BID

Rees Tree Service                                                     NO BID

Wright Outdoor Solutions                                           NO BID

Engineer’s Estimated Cost                                    $45,000.00


The Engineer’s estimated cost for the project was $45,000.00. The Municipal Utilities Department recommends award of the 2019 Deer Creek Trunk Sewer Extension Clearing and Grubbing project to J. Pettiecord, Inc.

FISCAL IMPACT: Yes
The 2019 Deer Creek Trunk Sewer Extension Clearing and Grubbing project is included in the 2019-2023 CIP for construction in 2019.
CITY MANAGER'S RECOMMENDATIONS:
Approve the motion to adopt RESOLUTION accepting a proposal from J. Pettiecord Inc., for the 2019 Deer Creek Trunk Sewer Extension Clearing and Grubbing project .