The NE 54th Street Bridge Replacement Over Branch of Fourmile Creek project includes the removal and replacement of the existing roadway bridge, reconstruction of the existing roadway and 8-ft. & 5-ft. sidewalk connections on NE 54th Street between NE Briarwood Drive and NE Hillcrest Drive in the City of Ankeny.
The construction improvements include earthwork, removals, construction of a 70’ x 32’ continuous concrete slab bridge with 10’ trail and 5' sidewalk, PCC street and sidewalk paving, storm sewer and water system infrastructure improvements, erosion control, traffic control, pavement markings, native grass and seed surface restoration, required testing and miscellaneous associated work necessary to complete the project.
The majority of this project's construction is being funded through the federal-aid Swap City Highway Bridge Program (HBP) and Surface Transportation Block Grant (STBG) Program, so the project was bid through the Iowa Department of Transportation (DOT). The bid opening for the project was held by the Iowa DOT on Wednesday, January 16, 2019. Four (4) bids were received as follows:
1. Herberger Construction Co., Inc. $1,278,252.59
2. Hentges, S.M. & Sons, Inc. $1,289,657.29
3. Jensen Construction Co. $1,452,260.85
4. Jenco Construction, Inc. $1,548,247.18
The engineer's estimate for the project was $1,284,406.60. The bids ranged from approximately 0.5% below to 21% above the estimate. The City reviewed the bid results both internally and with the project's engineering consultant. Herberger Construction Co., Inc., has previously completed projects of similar nature in this area, and they have the technical experience to undertake this project. It is recommended that the project be awarded to Herberger Construction Co., Inc., of Indianola, Iowa.
Pending project approval and award by the City Council, the contractor will have one hundred (100) working days to complete the project, and the Notice to Proceed is expected to be issued on or before May 13, 2019. It is anticipated that the project will be completed in the fall of 2019. |