SUBJECT: |
Consider motion to approve Change Order #5 to extend the substantial completion date from April 30, 2019, to May 31, 2019, and changing the final completion date from May 31, 2019, to June 30, 2019 for C.L. Carroll Co., Inc., at no additional cost for construction services on the Northwest Booster Station project.
|