ORIGINATING DEPARTMENT: COUNCIL GOAL:
Public Works Responsible Growth and Revitalization
ACTION REQUESTED:
Resolution
LEGAL:
No Review Required
SUBJECT:

2019 Crestrbuck Park Recreation Trail Replacement & Miscellaneous Trail Patches:  Consider motion to approve:  a) Final Change Order #1 increasing the contract amount by $32,160.85; b)  Certificate of Completion; c) RESOLUTION accepting the public improvements with Shekar Engineering P.L.C in the amount of $200,225.10; and d) Final Payment #4 in the amount of $40,225.38 / Release of Retainage in the amount of $10,011.25.

EXECUTIVE SUMMARY:

The actions before the Council are the approval of the final Change Order, acceptance of the Certificate of Completion, passage of a Resolution accepting the public improvements and approval of the final and retainage payments to Shekar Engineering P.L.C for the 2019 Crestbruck Park Recreation Trail Replacement & Miscellaneous Trail Patches project.

The 2019 Crestbruck Park Recreation Trail Replacement & Miscellaneous Trail Patches project is now complete.  A series of actions are needed in order to close out this construction project:

1) Approval of the Final Change Order #1 increasing the contract amount by $32,160.85.

 

2)  Engineer's Certificate of Completion:  The attached Certificate of Completion from the project engineer states that the work performed was in substantial compliance with the plans and specifications and that the final contract amount is $200,225.10.

3)  Resolution accepting the public improvements:  This Resolution approves and adopts the Engineer's Certificate of Completion for the 2019 Crestbruck Park Recreation Trail Replacement & Miscellaneous Trail Patches project and establishes the final contract amount to be $200,225.10.

 

4) Final Payment:  Shekar Engineering P.L.C. = $40,225.38

    Retainage Payment:  Shekar Engineering P.L.C. = $10,011.26

It is recommended that the retainage payment be approved for payment 31 days from the date of acceptance of the project, in accordance with the terms of the contract.

FISCAL IMPACT: Yes
The above payments will facilitate the final completion of this project which was funded through the Capital Improvements Program.
CITY MANAGER'S RECOMMENDATIONS:

It is recommended that the Council take the following actions:

 

1. Approve final Change Order #1 increasing the contract amount by $32,160.85.

2. Accept the Certificate of Completion from the project engineer for the 2019 Crestbruck Park Recreation Trail Replacement & Miscellaneous Trail Patches project.
3. Adopt the Resolution accepting the 2019 Crestbruck Park Recreation Trail Replacement & Miscellaneous Trail Patches project with Shekar Engineering P.L.C in the final contract amount of $200,225.10; and

4. Authorize final payment to Shekar Engineering P.L.C in the amount of $40,225.38 and release of retainage payment in the amount of $10,011.26 in accordance with the terms of the contract.

 
PREVIOUS COUNCIL/COMMISSION/BOARD ACTION(S):
June 3, 2019:  The council approved a motion to adopt a Resolution accepting the proposal from Shekar Engineering P.L.C in the amount of $168,064.25 for the construction of the 2019 Crestbruck Park Recreation Trail Replacement & Miscellaneous Trail Patches.
PUBLIC OUTREACH EFFORTS:
ACTION REQUESTED:
ADDITIONAL INFORMATION:
ATTACHMENTS:
Click to download
Certificate of Completion
Final Change Order
Resolution
Final Pay App (Release Retainage)