The actions before the Council are the approval of the final Change Order, acceptance of the Certificate of Completion, passage of a Resolution accepting the public improvements and approval of the final and retainage payments to Shekar Engineering P.L.C for the 2019 Crestbruck Park Recreation Trail Replacement & Miscellaneous Trail Patches project.
The 2019 Crestbruck Park Recreation Trail Replacement & Miscellaneous Trail Patches project is now complete. A series of actions are needed in order to close out this construction project:
1) Approval of the Final Change Order #1 increasing the contract amount by $32,160.85.
2) Engineer's Certificate of Completion: The attached Certificate of Completion from the project engineer states that the work performed was in substantial compliance with the plans and specifications and that the final contract amount is $200,225.10.
3) Resolution accepting the public improvements: This Resolution approves and adopts the Engineer's Certificate of Completion for the 2019 Crestbruck Park Recreation Trail Replacement & Miscellaneous Trail Patches project and establishes the final contract amount to be $200,225.10.
4) Final Payment: Shekar Engineering P.L.C. = $40,225.38
Retainage Payment: Shekar Engineering P.L.C. = $10,011.26
It is recommended that the retainage payment be approved for payment 31 days from the date of acceptance of the project, in accordance with the terms of the contract. |