The City Council approved the 2019-2023 Capital Improvement Program on January 21, 2019. The Annual Traffic Signal Improvement Program within the 2019-2023 Capital Improvement Program includes the NE 18th Street & NE Trilein Drive Traffic Signal project with design scheduled for Calendar Year 2019 and construction scheduled for Calendar Year 2020.
The project will construct a new traffic signal at the intersection, relocate a school zone flashing beacon, upgrade the fiber optic communication cable and pedestrian ramps, and patch pavement on the north leg. The construction project is estimated to cost approximately $480,000.
It is recommended that the NE 18th Street & NE Trilein Drive Traffic Signal project within the 2019-2023 Capital Improvements Program be authorized at this time, so the project can be let for bids in December 2019. This will support timely procurement of equipment for construction to start in June 2020 with expected completion in early fall 2020. |