The actions before the council are the acceptance of the certificate of completion, passage of a resolution accepting the public improvements and approval of the retainage payment to DDVI, Inc. for the Fire Station No. 3 project.
The project is now complete. A series of actions are needed in order to close out this construction project:
a. Architect's Certificate of Completion: The attached Certificate of Completion from the SVPA states that the work performed was in substantial conformance with the plans and specifications and that the final contract amount is $3,370,994.38.
b. Resolution accepting the public improvements: This resolution approves and adopts the engineer's Certificate of Completion and establishes the final contract amount.
c. Retainage Payment - DDVI, Inc. $55,699.72.
It is recommended that the retainage payment be approved for payment 30 days after project acceptance t in accordance with the terms of the contract. |