ANKENY CITY COUNCIL

Regular Agenda

January 20, 2020
5 : 30 PM

Gary Lorenz, Mayor
Mark Holm, Mayor Pro tem

Council Members: Bobbi Bentz, Jeff Perry, Kelly Whiting, Kerry Walter-Ashby
Print
ORIGINATING DEPARTMENT: COUNCIL GOAL:
Municipal Utilities Responsible Growth and Revitalization
ACTION REQUESTED:
Resolution
LEGAL:
No Review Required
SUBJECT:
Deer Creek Trunk Sewer Extension:  Consider motion to approve:   a) Certificate of Completion; b) RESOLUTION accepting the public improvement with J. Peddiecord, Inc.  in the amount of $68,400.00; c)  Final Payment #2 in the amount of $0.00 / Release of Retainage in the amount of $3,420.
EXECUTIVE SUMMARY:

The actions before the council are the acceptance of the Certificate of Completion, passage of a Resolution accepting the public improvements, and approval of the final and retainage payment to J. Peddiecord, Inc. on the Deer Creek Trunk Sewer Extension - Clearing & Grubbing Project.

The Deer Creek Trunk Sewer Extension - Clearing & Grubbing Project is now complete including all final punch-list items.  A series of actions are needed in order to close out this construction project:

 

1. Engineer's Certificate of Completion:  The attached Certificate of Completion from the project engineer states that the work performed was in substantial conformance with the plans and specifications and that the final contract amount is $68,400.00.

 

2. Resolution accepting the public improvements:  This resolution approves and adopts the engineer's Certificate of Completion on the Deer Creek Trunk Sewer Extension - Clearing & Grubbing Project and establishes the final contract amount to be $68,400.00.

 

3. Final Payment:  J. Peddiecord, Inc. = $0.00

    Retainage Payment:  J. Peddiecord, Inc. = $3,420.00

It is recommended that the retainage payment on the project be approved for payment 31 days from the date of acceptance of the project, in accordance with the terms of the contract.

FISCAL IMPACT: No
The above payments will facilitate the final completion of this project, which was funded through the Capital Improvements Program.
CITY MANAGER'S RECOMMENDATIONS:

It is recommended that the council take the following actions:

 

1. Accept the Certificate of Completion from the project engineer for the Deer Creek Trunk Sewer Extension - Clearing & Grubbing Project;

2. Adopt the Resolution accepting the Deer Creek Trunk Sewer Extension - Clearing & Grubbing Project with J. Peddiecord, Inc. in the final contract amount of $68,400.00; and 

 

3. Authorize final payment to J. Peddiecord, Inc. in the amount of $0.00 and release of retainage payment in the amount of $3,420.00 in accordance with the terms of the contract.

PREVIOUS COUNCIL/COMMISSION/BOARD ACTION(S):

February 4, 2019: Council held a public hearing; adopted plans, specifications, form of contract, and estimate of cost; awarded construction; and approved construction contract and bonds.

PUBLIC OUTREACH EFFORTS:
ACTION REQUESTED:
ADDITIONAL INFORMATION:
ATTACHMENTS:
Click to download
Certificate of Completion
Resolution
Final Payment Application