ANKENY CITY COUNCIL

Regular Agenda

May 4, 2020
5 : 30 PM

Gary Lorenz, Mayor
Mark Holm, Mayor Pro tem

Council Members: Bobbi Bentz, Jeff Perry, Kelly Whiting, Kerry Walter-Ashby
Print
ORIGINATING DEPARTMENT: COUNCIL GOAL:
Public Works Responsible Growth and Revitalization
ACTION REQUESTED:
Resolution
LEGAL:
No Review Required
SUBJECT:
Consider motion to adopt RESOLUTION accepting a proposal from TK Concrete, Inc. in the amount of $42,985.00 for the construction of the 2020 Georgetown and White Birch Park Shelter Pads project.
EXECUTIVE SUMMARY:

The action before the council is the adoption of a resolution accepting a proposal from  TK Concrete, Inc. for the 2020 Georgetown and White Birch Park Shelter Pads project.
 

The 2020 Georgetown and White Birch Park Shelter Pads project includes the installation of park shelter pads and adjacent sidewalk at both Georgetown and White Birch park.  The Georgetown Park construction area is located at 2625 NW Ash Drive and the White Birch Park construction area is located at the corner of SW 35th Street and SW White Birch Drive.

 

The construction improvements include mobilization to the site, approximately 44 CY of Class 10 excavation, the placement of a 2" subbase, 140 SY of 5" reinforced PCC pavement, 49 SY of sidewalk removals, 150 SY of 6" PCC sidewalk, the installation of 8 reinforced PCC shelter footings, conventional seeding and fertilizing with BFM hydromulching for both permanent and temporary seeding, and a roll-off concrete washout container.  Other associated improvements include any miscellaneous associated work necessary to complete the project.

 

Bid invitations were sent to fifteen (15) contractors that can complete this type of work.  Two (2) bid were received for the project as follows:

 

TK Concrete, Inc.                                    $42,985.00

MNM Concrete Specialties                     $43,188.00 

Engineer's Estimate                                $43,981.00

Public Works staff recommends that the project be awarded to TK Concrete, Inc..

FISCAL IMPACT: No
The cost for this project is included with the Annual Park Development Program in the 2020 - 2024 CIP.
CITY MANAGER'S RECOMMENDATIONS:
Approve the motion to adopt RESOLUTION accepting a proposal from TK Concrete, Inc.  for the 2020 Georgetown and White Birch Park Shelter Pads project.
PREVIOUS COUNCIL/COMMISSION/BOARD ACTION(S):
PUBLIC OUTREACH EFFORTS:
ACTION REQUESTED:
ADDITIONAL INFORMATION:
ATTACHMENTS:
Click to download
Resolution
Bid Tabulation
Location map