West First Street Widening and Improvements - Phase 1
Amendment #2 to Professional Service Agreement - Foth Infrastructure & Environment, LLC

EXECUTIVE SUMMARY:

Foth Infrastructure and Environment, LLC has completed the preliminary design and a portion of the final design of the West First Street Widening and Improvements - Phase 1 project associated with Amendment No. 1 in 2019.  The Public Works Department proposes to continue using Foth Infrastructure and Environment, LLC for the remainder of the final design engineering services for the project in 2020.  The scope of the remaining final design engineering services and the corresponding fees are shown in the attached Amendment No. 2 to the Professional Services Agreement.  A copy of the original Professional Services Agreement and Amendment No. 1 are also attached for reference.

 

There are three additional projects that are associated with the West First Street Widening and Improvements - Phase 1 project that are to be constructed in 2020, in advance of the Phase 1 project which will be constructed in 2021-2022.  These projects are the West First Street Joint Utility Trench project, the NW Northlawn Area Sanitary Sewer Improvements project, and the West First Street Temporary Traffic Signals project.  Amendment No. 2 also includes design engineering services and construction engineering services with Foth Infrastructure and Environment, LLC for these three projects.  A portion of the design engineering services for the West First Street Joint Utility Trench project was previously included with Amendment No. 1 in 2019.

 

The breakdown for Amendment No. 2 for all four projects for design engineering services and construction engineering services is listed below.

 

Design Engineering Services

West First Street Widening and Improvements - Phase 1 $120,870.00

West First Street Joint Utility Trench   $51,430.00

NW Northlawn Area Sanitary Sewer Improvements   $28,900.00

West First Street Temporary Traffic Signals   $14,500.00

 

Construction Engineering Services

West First Street Joint Utility Trench $149,240.00

NW Northlawn Area Sanitary Sewer Improvements     $6,870.00

West First Street Temporary Traffic Signals     $7,580.00

 

The total fee associated with Amendment No. 2 for the design engineering services and construction engineering services is $379,390.00.

It is recommended that the City Council approve Amendment No. 2 to the Professional Services Agreement with Foth Infrastructure and Environment, LLC.

FISCAL IMPACT: No
The design engineering services for the West First Street Widening and Improvements - Phase 1 project, the West First Street Joint Utility Trench project, and NW Northlawn Area Sanitary Sewer Improvements project, and the West First Street Temporary Traffic Signals project, and the construction engineering services for the West First Street Joint Utility Trench project, the NW Northlawn Area Sanitary Sewer Improvements project, and the West First Street Temporary Traffic Signals project, are included in the City's 2020-2024 Capital Improvement Program for 2020.
CITY MANAGER'S RECOMMENDATIONS:
PREVIOUS COUNCIL/COMMISSION/BOARD ACTION(S):
PUBLIC OUTREACH EFFORTS:
ACTION REQUESTED:

Action: Consider motion to approve Amendment No. 2 to the Professional Services Agreement increasing the contract amount by $379,390.00 with Foth Infrastructure and Environment, LLC for design engineering services on the West First Street Widening and Improvements - Phase 1 project ($120,870.00), the West First Street Joint Utility Trench project ($51,430.00), the NW Northlawn Area Sanitary Sewer Improvements project ($28,900.00), and the West First Street Temporary Traffic Signals project ($14,500.00) and for construction engineering services on the West First Street Joint Utility Trench project ($149,240.00), the NW Northlawn Area Sanitary Sewer Improvements project ($6,870.00), and the West First Street Temporary Traffic Signals project ($7,580.00).