The actions before the council are the approval of the final Change Order, the acceptance of the Certificate of Completion, passage of a Resolution accepting the public improvements, and approval of the final and retainage payments to Absolute Concrete Construction, Inc. on the NW 36th Street Widening - NW Ash Drive to North Ankeny Boulevard project.
The NW 36th Street Widening - NW Ash Drive to North Ankeny Boulevard project is now complete. A series of actions are needed in order to close out this construction project:
a) Approval of the Final Change Order #6 decreasing the contract amount by $25,077.95.
b) Engineer's Certificate of Completion: The attached Certificate of Completion from the project engineer states that the work performed was in substantial conformance with the plans and specifications.
c) Resolution accepting the Public Improvements: This Resolution approves and adopts the Engineer's Certificate of Completion on the NW 36th Street Widening - NW Ash Drive to North Ankeny Boulevard project and establishes the final contract amount to be $4,022,885.08.
d) Final Payment: Absolute Concrete Construction, Inc. = $944.30
Retainage Payment: Absolute Concrete Construction, Inc. = $144,144.25
It is recommended that the retainage payment be approved for payment 31 days from the date of acceptance of the project, in accordance with the terms of the contract.
|