Public Works Upgrade Essential Infrastructure
ACTION REQUESTED:
Resolution
LEGAL:
No Review Required
SUBJECT:

NW 36th Street Widening - NW Ash Drive to North Ankeny Boulevard: Consider motion to approve: a) Final Change Order #6 decreasing the contract amount by $25,077.95; b) Certificate of Completion; c) RESOLUTION accepting the public improvement with Absolute Concrete Construction, Inc. in the amount of $4,022,885.08; and d) Final Payment #16 in the amount of $944.30; and Retainage Payment in the amount of $144,144.25.

EXECUTIVE SUMMARY:

The actions before the council are the approval of the final Change Order, the acceptance of the Certificate of Completion, passage of a Resolution accepting the public improvements, and approval of the final and retainage payments to Absolute Concrete Construction, Inc. on the NW 36th Street Widening - NW Ash Drive to North Ankeny Boulevard project.  

 

The NW 36th Street Widening - NW Ash Drive to North Ankeny Boulevard project is now complete.  A series of actions are needed in order to close out this construction project: 

a) Approval of the Final Change Order #6 decreasing the contract amount by $25,077.95.

b) Engineer's Certificate of Completion: The attached Certificate of Completion from the project engineer states that the work performed was in substantial conformance with the plans and specifications.

c) Resolution accepting the Public Improvements:  This Resolution approves and adopts the Engineer's Certificate of Completion on the NW 36th Street Widening - NW Ash Drive to North Ankeny Boulevard project and establishes the final contract amount to be $4,022,885.08.

d) Final Payment: Absolute Concrete Construction, Inc. = $944.30

    Retainage Payment: Absolute Concrete Construction, Inc. = $144,144.25

 

It is recommended that the retainage payment be approved for payment 31 days from the date of acceptance of the project, in accordance with the terms of the contract.

 
 
FISCAL IMPACT: No
The above payments will facilitate the final completion of this project, which was funded through the Capital Improvements Program.
CITY MANAGER'S RECOMMENDATIONS:

It is recommended that the council take the following actions: 

 

1. Approve Final Change Order #6 decreasing the contract amount by $25,077.95.

 

2. Accept the Engineer's Certificate of Completion for the NW 36th Street Widening - NW Ash Drive to North Ankeny Boulevard project. 

 

3. Adopt the Resolution accepting the NW 36th Street Widening - NW Ash Drive to North Ankeny Boulevard project in the final contract amount of $4,022,885.08.

 

4. Authorize Final Payment in the amount of $944.30, and Retainage Payment in the amount of $144,144.25.

 
PREVIOUS COUNCIL/COMMISSION/BOARD ACTION(S):

December 20, 2021: The City Council approved a Resolution ordering construction and setting the bid opening date as January 11, 2022 and the public hearing date as January 18, 2022.

 

January 18, 2022: The City Council awarded the construction project and approved the construction contract and bond.

PUBLIC OUTREACH EFFORTS:
A Project Information Meeting for the adjacent property owners, businesses, and residents was held on September 8, 2021. Property owners, businesses, and residents received periodic update letters during the construction phase.  Additionally, periodic updates were posted on the City's interactive construction map website for the general public.
ACTION REQUESTED:
ADDITIONAL INFORMATION:
ATTACHMENTS:
Click to download
Change Order #6 (Final)
Certificate of Completion
Payment Application #16 (Final)
Resolution